Lighting · Module 6 of 6 · 1 hours

Show day, lighting

Show day, lightingThe instructor introduces this page

Rig, address, focus, program, run, and get it down again safely.

4 lessons · 2 paper · 2 the room

Every lesson is read, then do, then check.

The check carries its answer underneath it. Look only after you have tried — the attempt is what teaches, not the answer.

Lesson 1 of 4Paper · Needs nothing but a pen

The order of a lighting day

Read
Rig everything cold. Address it and write the patch sheet. Power and check every fixture responds. Focus with the stage empty and somebody standing where the performer will be. Program the looks. Then run it. Doing these out of order means climbing twice, and the ladder is where the time and the risk both live.
Do
Write the order out for a six-fixture show with the time you would give each stage.
Check

Why focus before programming rather than after?

Lesson 2 of 4The room · Needs real equipment · the Depot

Focusing needs a person standing there

Read
You focus a light on where a person will be, at their height, not on an empty floor. A beam that looks perfect on bare boards can be lighting somebody's chest and leaving their face dark. Somebody stands in; if nobody will, you stand in it yourself and look at a phone camera on a stand.
Do
Focus three fixtures on the plan using a marked performer position rather than a floor spot.
Check

Why is a floor spot a poor target?

Lesson 3 of 4The room · Needs real equipment · the Depot

Heat, power and the circuit nobody checked

Read
Fixtures draw current and conventionals get genuinely hot. Several on one circuit will trip it, usually at the worst moment, and a hot fixture near a curtain is a fire rather than an inconvenience. Know which sockets are on which circuit before you plug in, and keep fabric away from anything that gets warm.
Do
Mark the circuits on a room plan and spread a six-fixture rig across them.
Check

Six conventionals on one domestic circuit. What happens?

Lesson 4 of 4Paper · Needs nothing but a pen

De-rig cold, and count everything

Read
Fixtures stay hot long after they go dark. You let them cool, you take the safety off last after the clamp is supported, and you count the clamps and safeties back into the case because they are small, expensive and the first things to be left on a floor.
Do
Write a de-rig order for the rig you built, with the cooling step in the right place.
Check

What comes off last when taking a fixture down?

For whoever is teaching it

Instructor notes

  1. This module is a drill. Run it against a clock.
  2. Make somebody stand in for focus. The empty-floor habit is hard to break once it forms.
  3. Hot fixtures are a real risk and students under-rate it because LEDs are cool. Most buildings still own conventionals.
  4. Count clamps and safeties out loud at de-rig. It becomes a habit by repetition only.

Slide running order

What goes on the screen.

  1. The order of a lighting day, as six steps
  2. A beam focused on a floor spot versus on a person's face
  3. A room plan with circuits marked and load spread
  4. A de-rig sequence with the cooling step highlighted

If you want more

Extra credit

  1. Find the consumer unit in a building you use and work out how many circuits the hall is on.
  2. Time yourself writing a patch sheet for six fixtures.
  3. Watch a get-out at any venue that will let you, and note the order they work in.